DES MOINES – The DNR Air Quality Bureau has the following draft permits up for review. The permits help protect Iowans’ health and the air where we live. DNR’s permitting staff review the applications to ensure facilities comply with state and federal air quality standards. The public has the right and is encouraged to comment on draft permits. DNR considers public comments before finalizing the permits. Submit comments in writing to the assigned permit writer before 4:30 p.m. on the last day of the comment period.

Construction Permits

DNR engineers review and issue construction permits to facilities before they build new or modify existing sources of air pollution. The public may review the following air quality construction permits available online at https://idnraqrr.iowadnr.gov/ConPermitSearch or through the EASY Air Public Inquiry Portal and then click the Public Notice tab.

Buena Vista CountyPlatinum Crush, LLC, 5956 70th Ave., AltaProject No. 25-374

Modification of existing PSD permits to correct equipment capacities, modify production limits, and modify operational conditions.  The public comment period ends September 5. 

Monroe County

Cargill, Inc - Eddyville, 17540 Monroe-Wapello Rd, Eddyville

Project No. 26-178

The facility is replacing the Gluten Flash Dryer Conveying II baghouse. Public comment period ends September 9.

Cargill, Inc - Eddyville, 17540 Monroe-Wapello Rd, Eddyville

Project No. 26-180

The facility is replacing the Gluten Flash Dryer II burners. Public comment period ends September 9.

Cargill, Inc - Eddyville, 17540 Monroe-Wapello Rd, Eddyville

Project No. 26-220

The facility is replacing two corn receiving elevators. Public comment period ends September 9.