Construction, installation or modification of any wastewater disposal system including sanitary sewer extensions requires a construction permit issued by the Department. Review of applications for construction permits shall be based on the criteria contained in the "Iowa Wastewater Facilities Design Standards," the Ten States Standards, applicable federal guidelines and standards, standard textbooks, current technical literature and applicable safety standards. To the extent of any conflict between the above criteria the "Iowa Wastewater Facilities Design Standards" standards shall prevail (567 IAC 64.2(9)).
A construction permit shall not be required for storm sewers or storm water disposal systems that transport only storm water, any new disposal system or extension or addition to any existing disposal system that receives only domestic or sanitary sewage from a building, housing or occupied by 15 persons or less.
Applications for a construction permit must be submitted to the Department at least 120 days in advance of the date of start of construction. The Department will issue a construction permit within 60 days of receipt of a complete application or denying the construction permit in writing unless a longer review period is required and the applicant is so notified in writing. The construction permit shall expire if construction has not commenced within one year of the date of issuance thereof. The Department may grant an extension of time to commence construction if it is necessary or justified.
Rules
Applicable rules for wastewater construction permitting are located in Chapter 567 IAC 64 of the Iowa Administrative Code. The current Iowa Wastewater Facilities Design Standards are located on the Design Standards Webpage.
New Permit Process Documents
Permitting Process Manual Documents
| Wastewater Engineering Construction Permitting Process Manual, Updated 1/11 |
|
Manual |
Manual |
| Wastewater Construction Permitting Process Flow Chart, Updated 9/10 |
|
|
Construction Flow Chart |
| Wastewater Construction Antidegradation Process Flow Chart, Updated 9/10 |
|
|
Antidegradation Flow Chart |
| Exhibit 1: Planning and Design Loan Fact Sheet, Updated 2/09 |
|
Exhibit 1 |
Exhibit 1 |
| Exhibit 2: Project Initiation Meeting Sample Agenda, Updated 9/10 |
|
Exhibit 2 |
Exhibit 2 |
| Exhibit 3: Waste Load Allocation Form and Instructions, Updated 9/11 |
|
Exhibit 3 |
Exhibit 3 |
| Exhibit 4: Facility Planning Scope of Study Checklist |
|
Exhibit 4 |
Exhibit 4 |
| Exhibit 5: SRF Environmental Review Checklist, Updated 2/09 |
|
Exhibit 5 |
Exhibit 5 |
| Exhibit 6: SRF Environmental Review Public Hearing Notice Example, Updated 2/09 |
|
Exhibit 6 |
Exhibit 6 |
| Exhibit 7: SRF Environmental Review Public Hearing Checklist, Updated 2/09 |
|
Exhibit 7 |
Exhibit 7 |
| Exhibit 8: CWSRF Intended Use Plan Application, Updated 8/12 |
|
Exhibit 8 |
Exhibit 8 |
| Exhibit 9A: Preliminary Review of Antidegradation Alternatives Analysis, Updated 9/10 |
|
Exhibit 9A |
Exhibit 9A |
| Exhibit 9B: Preliminary Review of Facility Plan Checklist, Updated 1/12 |
|
Exhibit 9B |
Exhibit 9B |
| Exhibit 10A: 60 Percent Preliminary Plan and Specification Submittal - Sewers and Force Mains, Updated 9/10 |
|
Exhibit 10A |
Exhibit 10A |
| Exhibit 10B: 60 Percent Preliminary Plan and Specification Submittal - Wastewater Pumping Station, Updated 9/10 |
|
Exhibit 10B |
Exhibit 10B |
| Exhibit 10C: 60 Percent Preliminary Plan and Specification Submittal - Wastewater Treatment Facilities, Updated 9/10 |
|
Exhibit 10C |
Exhibit 10C |
| Exhibit 11A: Design Schedule A, Updated 9/10 |
542-3129 |
Exhibit 11A |
Exhibit 11A |
| Exhibit 11B: Design Schedule F |
542-3099 |
Exhibit 11B |
Exhibit 11B |
| Exhibit 11C: Design Schedule G, Updated 10/11 |
542-3100 |
Exhibit 11C |
Exhibit 11C |
| Exhibit 12: Instructions for Compliance with SRF Cross-Cutters - Bidding and Procurement Process, Updated 2/10 to include Davis-Bacon requirements |
|
Exhibit 12 |
Exhibit 12 |
| Exhibit 12a: SRF Required Front-End Specifications, Updated 2/10 to include Davis-Bacon requirements |
|
Exhibit 12a |
Exhibit 12a |
| Exhibit 13: CWSRF Bid Document Checklist, Updated 8/12 |
|
Exhibit 13 |
Exhibit 13 |
| Exhibit 14: CWSRF Extended Financing Worksheet, Updated 2/09 |
|
Exhibit 14 |
Exhibit 14 |
Permit Application Forms